年中盘点:雄岚钢构今年上半年交付覆盖 50 余国Mid-Year Review: Xionglan Delivered to 50+ Countries in H1

公司动态 · Company News Xionglan Engineering Team

2026 年上半年,我们完成出口订单 120 余个,项目遍布东南亚、中东、非洲与拉美,最远一批构件发往智利阿里卡港。In H1 2026 we completed 120+ export orders across Southeast Asia, the Middle East, Africa and Latin America — the farthest shipment landed at Arica, Chile.

2026 年上半年,雄岚完成出口钢构订单 120 余个,累计出货超过 26,000 吨,覆盖 50 多个国家和地区。单批最远的一组多层框架构件发往智利阿里卡港,全程海运 42 天,现场安装 38 天完成。

产能方面,奉贤基地新增一条数控切割线后,月产能提升至 6,500 吨,常规项目从图纸确认到发运平均缩短 6 天。

感谢每一位客户的信任。下半年我们将继续把重心放在交期稳定性与文件合规性上——这两件事,是海外项目最大的隐形风险。

In the first half of 2026, Xionglan completed 120+ export orders totalling over 26,000 tonnes, delivered to more than 50 countries and regions. The longest single shipment — a multi-story frame — sailed to Arica, Chile: 42 days at sea, erected in 38 days.

On capacity: after adding a CNC cutting line at our Fengxian plant, monthly output reached 6,500 tonnes, cutting average lead time from drawing approval to shipment by 6 days.

Thank you to every client for the trust. For H2 we stay focused on delivery stability and documentation compliance — the two biggest hidden risks in overseas projects.

钢构出口钢结构出口公司steel structure exportchina steel building manufacturer
需要钢结构方案与报价?/ Need a steel structure quote?

上海雄岚钢结构 · 出口 60+ 国家 · EN 1090 CE 认证 · 24 小时内工程师回复

联系工程师 / Talk to an engineer 查看产品体系